Before starting any renovation or building works in Valencia you need the right municipal permit. The rules changed on 28 January 2026: the City Council now applies a new licensing ordinance and the old prior communication of works (comunicación previa) no longer exists. This guide explains which procedure your building permit in Valencia requires, what documentation is needed, how much it costs and how long it really takes.
At BTTEstudio Arquitectura we handle these applications every week as part of our full renovations and turnkey projects.
What changed in 2026: the end of the prior communication of works
Until January 2026 there were three routes: prior communication, responsible declaration and licence. Today there are two: the responsible declaration (declaración responsable) and the building licence (licencia de obras). Minor works that used to go through prior communication (replacing floors, wall tiles, sanitaryware, painting) are now processed as a responsible declaration for maintenance works, with simplified documentation.
Summary: which procedure your works need
| Type of works | Procedure | When you can start |
|---|---|---|
| Maintenance: floors, wall tiles, painting, sanitaryware | Responsible declaration (maintenance) | On filing |
| Renovation changing the layout or the installations, without touching the structure | Responsible declaration (renovation) | On filing |
| Structure, extension, change of use, listed building, new build | Building licence | Once it is granted |
1. Responsible declaration of works
This is the usual route for renovating a flat in Valencia. It covers maintenance works and renovations that do not alter the structure or affect listed elements.
Maintenance works (formerly prior communication)
Replacement of floors, wall tiles and suspended ceilings, renewal of plumbing and electrics, sanitaryware, interior joinery, plastering and painting. Documentation: a descriptive report and an itemised budget.
Renovations changing the layout or the installations
A qualified professional is required. Documentation:
- Technical report signed by a qualified professional.
- Drawings of the existing and proposed layout.
- Itemised budget.
- Basic health and safety study.
- Construction waste management study.
- Appointment of the technical site management.
Advantage: you can start the works as soon as you file it through the electronic register, with complete documentation and the fee and the ICIO tax paid. The City Council may check it afterwards and ask you to correct it.
Deadlines you must meet: 6 months to start and 24 months to finish. No extension is allowed except in cases of force majeure.
2. Building licence (major works)
It is compulsory when the works:
- Modify the structure (slabs, columns, beams).
- Increase the floor area.
- Change the use of the property (from commercial premises to housing, for example).
- Affect listed buildings or protected areas (Cabanyal, Ciutat Vella).
- Are a new build, a complete refurbishment or a demolition.
Documentation: basic and detailed design project, health and safety study, site management team (architect and technical architect) and, in listed buildings, the heritage reports. Unlike the responsible declaration, you cannot start until the licence has been granted.
Real timescales: in our experience, between 12 and 24 months, depending on the municipal workload and the complexity of the project.
How to shorten the timescales: ECUVs
ECUVs are private bodies that collaborate with the Administration, regulated by the Valencian Government since 2020. They verify the project before it is filed and issue a certificate of conformity, so the application reaches the City Council already technically reviewed. Using them is voluntary and has a separate cost.
In our experience, processing with an ECUV shortens licence timescales by 50% to 60%. We use them for major works licences and for listed buildings, and on each project we assess whether it is worthwhile.
How much it costs: municipal fee and ICIO tax in 2026
Two items are paid, both before filing and both calculated on the construction cost (excluding VAT, professional fees and the contractor’s profit).
1. Municipal planning fee
| Construction cost | Fee |
|---|---|
| Up to €6,010.12 | €140.90 |
| €6,010.12 to €30,050.61 | €253.54 |
| €30,050.61 to €60,101.21 | €751.31 |
| €60,101.21 to €150,253.03 | €1,638.97 |
| €150,253.03 to €300,506.05 | €3,756.28 |
| €300,506.05 to €601,012.10 | €7,982.11 |
2. ICIO tax
The tax on constructions, installations and works (ICIO) is 4% of the construction cost (rate in force in 2026).
Example: a renovation with a construction cost of €40,000 pays €751.31 in fees and €1,600 in ICIO: €2,351.31 in total. Professional fees and, if you use one, the ECUV are added to that.
How to apply for a building permit in Valencia, step by step
- Define the scope of the works and confirm whether the building is listed.
- Determine the procedure: responsible declaration or licence.
- Prepare the technical documentation.
- Pay the fee and the ICIO tax by self-assessment.
- File it through the City Council’s electronic office using the standard form.
- With a responsible declaration, start the works; with a licence, wait for the decision.
Legalising existing works and homes in Valencia
Works carried out without a permit can be legalised provided they comply with current regulations. They are processed with the same permit that would have applied (responsible declaration or licence), stating that the purpose is legalisation.
The risk is that the works do not comply with the regulations in force: the Spanish Technical Building Code (CTE), the Valencian housing design and quality standards (DC-09) or the General Urban Plan (PGOU). In that case they must be adapted before they can be legalised. That is why the first step is always a technical survey of what has been built.
What about the activity licence?
If the works are for opening a business, in addition to the works permit you need the activity permit, and both are processed in a coordinated way. In our commercial premises and office fit-out projects the activity and opening licences are included. See our services.
Frequently asked questions about building permits in Valencia
Does the prior communication of works (comunicación previa) still exist in Valencia?
No. Since the ordinance that came into force on 28 January 2026, those works are processed as a responsible declaration for maintenance works.
Can I start the works on the day I file the responsible declaration?
Yes, provided the documentation is complete and you have paid the municipal fee and the ICIO tax.
How much does the permit to renovate a flat in Valencia cost?
It depends on the works budget. With a construction cost of €40,000, the municipal fee and the ICIO tax add up to €2,351.31.
What if my building is listed?
Works affecting listed elements cannot be processed by responsible declaration: they need a building licence.
Is it compulsory to use an ECUV?
No, it is voluntary. It pays off in major works licences and in listed buildings, where the time saved is greatest.
Do you need a building permit in Valencia?
At BTTEstudio we design the project, handle the permit and carry out the works with our own construction company and a single point of contact. More than 14 years and more than 200 completed works back us. If you already have a project, we can also take on just the site management.
Tell us about your project · Call us: +34 960 055 332 · WhatsApp
You may also be interested in: New-build in Valencia: how BTTEstudio works step by step and How to avoid the most common mistakes in full refurbishments.
Information updated in November 2026. Official source (in Spanish): Valencia City Council electronic office. Fees and the ICIO tax may change every year.